Kipling Estates shared drain tile drainage problems
A resident at 1004 Conrad Lane says storm water backs into her basement because a shared drain tile serving five homes is backing up and no one — including the village — can locate where it runs. She's spent about $2,000 on plumbers and scoping and asked the village to help find a workable connection point before winter.
River Lift Station maintenance
Shorewood's Seil Road lift station handles about 65% of village wastewater and gets overwhelmed in heavy rains. This study is step one of an expansion that could divert flow and keep up with growth on the village's west side.
Western sewer and water expansion and future development
Shorewood is nearing its 4-million-gallon-per-day wastewater capacity limit with Joliet. Paying $130,000 now to reserve space in an upsized Rock Run sewer line avoids far costlier permitting later when the village needs more capacity.
Prohibition of private and communal wells
A new ordinance permanently bans potable wells in the area around old BP Amoco fuel-tank contamination near E. Jefferson — the last affected property just connected to village water. If you're in that zone, you can't drill a well, ever.
US 52 water-sewer extension
The village is extending water and sewer service along Route 52 west of the tracks and just cleared ComEd's easement hurdle. Construction is coming to that corridor.
River Road Lift Station Expansion
A new annual program to inspect and clean the River Road lift station, starting with Airy's $15,000 job, to avoid emergency failures like one a few years back on Seil Road.
Des Plaines River crossing reroute
After three years of permitting, the Army Corps said no to crossing the river at the planned location due to the electric fish barriers. A new route is in the works and the Corps has blessed it, but it adds an estimated $15 million.
Grand Prairie Water Commission construction and WIFIA financing
The section well and high/low pumping station projects are moving forward, with mobilization starting in April 2026. The Village is closing a $600+ million WIFIA loan this week, and interest will accrue on draws even before payments begin. Cost, rate structures, and funding from state and federal legislators are all live questions for ratepayers.
Grand Prairie Water Commission Progress
Bids for large water valves came in between $6.4 and $10.6 million against a $12.5 million budget — good news for the water project. Officials will verify quality before awarding rather than just taking the low bid.
Metro Fibernet fiber network agreement
The Board approved a master license agreement letting Metro Fibernet (T-Mobile Fiber) build an all-underground fiber network in town. Residents will get mailed notices, postcards, and yard signs before construction, and the company promises same-day restoration of any digging. This means a new gig-speed internet option competing with Comcast and AT&T.