Village Hall entry project rebid
Summary
Bids for replacing the brick pavers at Village Hall came in at $152,000-$183,000 against a $71,629.87 estimate, so the board rejected them all and will rebid, hoping for better market timing.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 2, 2026.
Impact analysis
The village budgeted $150,000 for design and construction and will rebid to try to land under it.
Taxpayers avoid paying an inflated bid while the entrance design improves.