North Main Street TIF Project Delay
Summary
The city puts up to $87,784 into redeveloping the old Main Street building, with the last payment tied to landing a sales-tax-producing tenant.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 15, 2026.
Impact analysis
City pays up to $87,783.95 in TIF incentives over three years.
Downtown: the vacant building gets redeveloped and the square gains a business.
Mentions & discussions (3)
City Council โ June 15, 2026
The old Foster's building TIF redevelopment hit wood rot and mortar failure, so the completion deadline moved from June 30 to August 31.
City Council โ March 2, 2026
The city puts up to $87,784 into redeveloping the old Main Street building, with the last payment tied to landing a sales-tax-producing tenant.
City Council โ February 16, 2026
Developer Cliff Veer wants city TIF help to restore the historic 122 N. Main building into two tenant spaces. The project cost dropped to about $383,426, and the city would reimburse up to $87,783.95 in three installments, with the last tied to a signed lease from a sales-tax-producing business. Council members voiced strong support, calling it an investment in saving downtown.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Washington
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.