Fire Department HVAC repairs and budget transfer
Summary
Replacing two more rooftop units at Fire House Station 25 came in at $45,261 — about $10,500 over the $35,000 budget — so the contract was deferred to the next meeting when all trustees can weigh in.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
$45,261 contract, requiring a $10,500 budget amendment funded by savings on the Gardner Road bridge project.
Firefighters at Station 25 get working heat and ventilation.