Green Alley Reconstruction Project
Summary
Five crumbling alleys from Haas to Highdorn will be rebuilt as green alleys under a roughly $900,000 contract, with MWRD paying about $393,000.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Apr 28, 2026.
Impact analysis
Village share roughly $500,000 of the $895,087.50 contract.
Residents and property owners along the five reconstructed alleys.
Mentions & discussions (2)
Village Board - Apr 28, 2026
Five crumbling alleys from Haas to Highdorn will be rebuilt as green alleys under a roughly $900,000 contract, with MWRD paying about $393,000.
Village Board - Apr 14, 2026
Bids open April 16 for the green alley reconstruction project, funded by roughly $400,000 from the MWD partnership, covering alleys along Roosevelt from Haas to High.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Westchester
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.