Civic Issues
Topics getting the most attention in Westchester public meetings, ranked by how frequently they are discussed.
10 issues in water utilities
Broadview-Westchester Joint Water Agency agreement
The Village locked in two state revolving-loan deals — 0% for lead service line replacement and 2.16% for water main replacement — to fix aging pipes in areas with a history of breaks. Written comments on the project plan are open for ten days after the hearing.
Replacing the Public Works underground fuel system
The Village's 1970s-80s underground fuel tanks face a 2028 state compliance deadline. Rather than spend $100,000+ patching them, the Village is building a $238,000 above-ground fuel island with a DEF dispenser, then removing the old tanks in FY 2028 with 60% IEPA reimbursement.
Sanitary sewer cleaning and televising program
A Windsor Drive family lost their renovated basement to sewer backups during the July 27 and August 1 storms, discovered asbestos requiring expensive abatement, and has been displaced from their home while their insurer stalls. Neighbors were hit too — the village says the system can't handle storms over about 2.5 inches of rain per hour, and it's an area-wide problem.
Water bill burden on seniors
A resident said her water bill jumped from $216 to $366 and asked what help exists for seniors in the suburbs. Staff pointed to PLCCA assistance and village payment plans, and the website has a water rates page. Trustees also flagged a suspicious 'Wildfire' credit card charge given what residents are paying.
Emergency notification system switch to Everbridge
The village has switched from Code Red to Everbridge for emergency alerts. Residents must re-register — even if they were signed up before — on the website homepage to keep getting water main break, snow parking, and road closure alerts.
Water main replacement program and $55M loan strategy
Public Works has repaired 11 water main breaks since January 1 — most from mains dating to the 1920s — amid extreme cold, plus two lead service line replacements and 17 snow events using 1,600 tons of salt.
New water agency leadership
Trustee Terrance Jones took over the village's seat on the Broadview-Westchester Joint Water Agency, replacing Peter Marzano — the body that helps govern the village's water supply.
Sewer point repairs and concrete restoration
Ten failing sewer pipe sections were found during camera inspections — five will be dug up by John Neri Construction, five done in-house. Impressive Construction will fix winter-damaged curbs, sidewalks and driveway aprons.
Water System Leak Detection
The new water meter system is already paying off: staff found leaking hydrants and can now measure daily water loss against Broadview's pumping station and fix it.
Water system improvements and lead service line replacement
The village held its required public hearing on an Illinois EPA low-interest loan plan. Lead service line replacement comes at 0% for 30 years and water main work at 1.62%; the first year's project is roughly $11.6 million covering about 2.5 miles. Residents learned homes may connect free when their street is rebuilt, and all lead must be out by 2040.