Temporary Moratorium on Data Centers and Battery Energy Storage
Summary
The city's 180-day moratorium expires mid-January. A survey of ~1,000 residents found 84% oppose data centers, with top concerns being utility costs and water use. Staff outlined regulations the city can adopt — special use permits, setbacks, noise limits, cooling-system standards, and decommissioning guarantees — but warned an outright ban would likely fail in court.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.
Impact analysis
The existing data center pays about $343,000 a year in property taxes, of which the city's share is roughly $17,000.
Residents gain a chance to shape rules before new data centers arrive, and the city keeps tax and utility revenue.
Residents near potential data center sites could face noise, water use and utility cost impacts if regulations fall short.
Mentions & discussions (5)
City of West Chicago City Council — November 2, 2026
The city's 180-day moratorium expires mid-January. A survey of ~1,000 residents found 84% oppose data centers, with top concerns being utility costs and water use. Staff outlined regulations the city can adopt — special use permits, setbacks, noise limits, cooling-system standards, and decommissioning guarantees — but warned an outright ban would likely fail in court.
City of West Chicago City Council — August 17, 2026
Residents fear data centers strain power and water and hurt property values; the council nonetheless granted the first exception for a battery storage facility near the airport, saying fairness required it.
City Pauses New Data Center and Battery Storage Approvals
City Pauses New Data Center and Battery Storage Approvals City of West Chicago, Illinois
City of West Chicago City Council — July 20, 2026
The council approved a temporary ban on data center facilities and battery energy storage systems in every zoning district — a pause while the city studies how it wants to handle these facilities.
City of West Chicago City Council — July 6, 2026
The council passed a six-month ban on new data centers and battery storage in all zoning districts to give the city time to study impacts. Residents learned a data center is already under construction on Washington Street because the 2024 council allowed such uses by right.
Related development
Temporary Moratorium on Data Center Facilities and Battery Energy Storage Systems
No new data centers or battery storage facilities can come in for now, giving the city time to write rules residents are more comfortable with.
TPE IL DU199 battery energy storage system
Allows a battery storage facility to keep its ComEd interconnection queue position; officials said fire risk is manageable but public questions remain.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for West Chicago
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.