1 N. Cass ComEd relocation
Summary
After nearly ten years, the village is paying ComEd's $1.6 million construction deposit to relocate utilities at 1 N. Cass. Construction, estimated at $2 million total, could start by September once the BNSF railroad permit arrives.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 23, 2026.
Impact analysis
A $1.6 million deposit now, against an estimated $2 million total construction cost, with the village billed or refunded the difference.
Residents and businesses near Cass Avenue, whose streetscape improves once the overhead lines are relocated.