Burlington Avenue realignment and downtown parking
Summary
crews hit far more contaminated soil than the design anticipated, adding $177,869 and pushing the project to about $1.8 million.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 12, 2026.
Impact analysis
Project total climbs to about $1.8 million, up $177,869.
The realignment supports downtown projects including Sentinel Station.
Taxpayers absorb the unplanned disposal costs.
Mentions & discussions (3)
Village Board - Nov 12, 2026
crews hit far more contaminated soil than the design anticipated, adding $177,869 and pushing the project to about $1.8 million.
Planning & Zoning Commission - Jul 8, 2026
The Village's North Lincoln Street lot was already designed to hold a future parking garage, and the commission discussed whether the Linden parking lot should be Village-owned or become a garage someday. The developer is open to the idea but not committed.
Village Board - Mar 5, 2026
The road realignment will close Burlington for construction and eventually remove a downtown parking lot to make way for a future development. Restaurant owners say it threatens their livelihoods โ one has already lost wedding bookings โ while others say parking isn't actually scarce. Staff promised aggressive communication and mitigation.
Related development
Holladay Properties PUD โ 1 North Cass Avenue / 14-20 North Linden Avenue (PZC 011-2025)
Adds density near the Metra station, replaces a public lot with 26 licensed public spaces, and could break ground by Q3 2027.
735 N. Cass Avenue Rezoning
The building becomes marketable for light industrial tenants, but M zoning allows more intense uses by right in a building not designed for them.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Westmont
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.