The board awarded the street rebuild to Schroeder Asphalt at a low bid about 15% under the engineer's estimate, hired the construction engineer, and appropriated $1.5 million in motor fuel tax funds.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 25, 2026.
Impact analysis
Low bid of about $1.34 million came in under the $1.7 million budget, plus a $150,000 grant.
Residents and drivers on Des Moines Street get a rebuilt road.
Mentions & discussions (1)