North Elevated Water Storage Tank Completion
Summary
ComEd changed the electric hookup plan mid-construction, adding $143,275 and pushing the tower's electric run about 500 feet instead of the planned ~200. The tower should be online by end of 2026, and it's up for a national 'Tank of the Year' contest — residents can vote through October 16.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 15, 2026.
Impact analysis
An extra $143,275 on a project already at about $6 million, though $1.65 million of it was forgiven loan money.
Everyone on the north water system gets a new 1-million-gallon tower by year's end.
Village ratepayers absorb the added cost caused by ComEd's late change.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Westmont
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.