Public Works Capital Projects Update
Summary
A $2.96 million watermain replacement on Park, Chicago and Willard streets — 10% under estimate with 16 bidders — will be built in spring and summer 2026, meaning construction disruption in that neighborhood.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Aug 20, 2026.
Impact analysis
$2,960,385 for construction plus $250,690 for construction engineering.
Residents on those streets get modern water mains and better service reliability.
Neighbors will face spring/summer construction disruption.
Mentions & discussions (2)
Village Board - Aug 20, 2026
Big progress across town: the North Water Tower is finished (waiting on ComEd), Burlington Avenue reopens this weekend, the water main replacement is 75% done, and 293 storm incidents were handled across five events.
Village Board - Jan 8, 2026
A $2.96 million watermain replacement on Park, Chicago and Willard streets — 10% under estimate with 16 bidders — will be built in spring and summer 2026, meaning construction disruption in that neighborhood.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Westmont
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.