Medium PriorityRoadsopen

Residential Alley 7S Reconstruction

Summary

The next alley rebuild — between 55th and West Quincy, Washington to Hudson — goes to Schroeder Asphalt at a bid roughly 23% under estimate. Part of a worst-first alley program now in its fifth year.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Apr 2, 2026.

Impact analysis

💰Financial impact

$1,145,663.62 construction contract, plus $155,550 in engineering — a favorable bid climate saved taxpayers money.

✅Who benefits

Residents along the alley who rely on it for garage access, garbage pickup and snowplowing.

⚠️Who could be affected

Temporary construction disruption for neighboring homes.