Water and sewer rate increase and Cedar Run water main
The village hired Clark Dietz for up to $222,000 in engineering work on replacing the Cedar Run watermain — part of ongoing water system upkeep.
Stormwater Master Plan Update
Village maps of its storm sewer system have errors, so the Board renewed engineering services with Gewalt Hamilton for a fourth and final year, up to $750,000, to finish cataloging pipes by the end of 2026.
Milwaukee/Hintz water main project on schedule
The water main work at Milwaukee and Hintz will wrap up by the end of August — good news for east-side drivers using it as a detour route.