West Main Street project IDOT funding

The committee is considering spending $228,000 in TIF 3 funds to have Kaskaskia Engineering Group finalize design plans for a streetscape upgrade along West Main Street between 12th and 17th streets. This is the design phase — construction would come later.

5 mentions (3 this month)Last discussed Nov 16, 2026
HighRoads

FY2027 Street Program Contracts

The city's yearly purchasing contracts for aggregates, asphalt, culverts and concrete — the raw materials behind street repairs — were up for renewal at a combined cost near $365,500.

4 mentions (1 this month)Last discussed Nov 2, 2026
HighRoads

Parking congestion on South 5th Street at West Cleveland

Residents say apartment-complex tenants parking on South 5th make the turn from West Cleveland dangerous and the street is deteriorating. The committee approved alternating no-parking to keep the street clear.

2 mentionsLast discussed Jun 15, 2026
HighRoads

E. Monroe, Abend and E. Adams street improvements

A $383,447 contract with KRB Excavating would resurface three east-side streets with new sidewalks, curbs, and patching. This directly affects residents on those streets.

2 mentionsLast discussed Jun 1, 2026
HighRoads

Freeburg Avenue roundabout at IL-158/IL-13

The state-federal roundabout project at IL 158 and IL 13 needs the city to sign a joint funding agreement, but the language could make Belleville cover unlimited cost overruns plus all lighting and curb maintenance on state-owned legs of the intersection. Council tabled it until IDOT responds.