Iron Flats
Description
Manager Stewart reported Iron Flats is scheduled to close June 11, with building plans preliminarily approved by staff and construction expected to start late summer with completion next spring.
Impact summary
A major development moving toward construction, with property closing expected by May.
At a glance
- Hearings
- 4
- Public comments
- 0
- Total mentions
- 4
Last vote · Board of Trustees
Last discussed Jun 9, 2026.
Meeting timeline (4)
Board of Trustees (Special) - Jun 9, 2026
The board released the first $1 million milestone payment to Horizon so the developer can close on the Iron Flats property this week, with construction mobilization expected by July and completion targeted for the second half of 2027.
Board of Trustees (Regular) - Jun 2, 2026
Manager Stewart reported Iron Flats is scheduled to close June 11, with building plans preliminarily approved by staff and construction expected to start late summer with completion next spring.
Board of Trustees (Regular) - May 7, 2026
Permits for the Iron Flats project are ready to be issued once contractors register and the property closing is confirmed; actual construction may begin around August.
Board of Trustees (Regular) - Mar 10, 2026
The developer submitted an updated building permit application; staff hope to comment next week, and the developer aims to close on the property by May.
Related issues (2)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Carpentersville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.