Iron Flats Project TIF milestone payment
Summary
The Iron Flats developer closed on the property but needed more time, so the PUD deadline stretched to March 2028 — construction mobilization is still expected in July.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 16, 2026.
Impact analysis
$1 million released now from the TIF fund, with $5 million more possible in future milestones; the village projects a tax-base jump from $33,000 to $750,000.
The developer gains time; the village gains a completed project eventually.
Trustee Malone argues residents are harmed if taxpayer money goes to a developer not paying prevailing wages.
Mentions & discussions (2)
Board of Trustees (Regular) - Jun 16, 2026
The Iron Flats developer closed on the property but needed more time, so the PUD deadline stretched to March 2028 — construction mobilization is still expected in July.
Board of Trustees (Special) - Jun 9, 2026
The village is paying out $6 million in incentive loans to Horizon Development Group in four milestones to jump-start the Iron Flats project at Western Avenue and Main Street. The first $1 million was released at this meeting to coincide with the property closing. The village projects a big tax-base gain once the project is done, but one trustee objected to the wage terms.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Carpentersville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.