Civic Issues
Topics getting the most attention in Carpentersville public meetings, ranked by how frequently they are discussed.
9 issues in taxes budget with medium priority
Structural Steel Bid Shortage and Bidding Waiver
No contractor bid on the structural steel package because data center projects are hoovering up steel and steelworkers. The Village solicited bids through unconventional means and included language letting the Board waive formal bidding rules to keep the project on schedule and budget.
Insurance Policy Renewal ($643,413)
The Village's business and workers' compensation insurance costs $643,413 for the coming year — part of the cost of doing business that shows up in the budget.
Assistant Community Development Director resignation
Tim Brinkmann, who has led planning staff work, is leaving for a private-sector developer job — the village will need to fill his role.
Kane County property tax levy
Trustee Frost flagged a nearly $2.3 million Kane County property tax levy increase following the county's $402.9 million budget, stressing to residents that Carpentersville has kept its own tax flat.
FY2025 Annual Audit Results
The village's independent auditor gave Carpentersville a clean, unmodified opinion for the 12th consecutive year, with no internal control weaknesses found. The board formally accepted the report.
Regional transit governance (NETA Act) impact on Kane County
County board member Chris Kious announced a free 24/7 county emergency alert system, a unified countywide paratransit service for seniors and disabled riders, and a new Kane County clerk/health office at Randall Road and I-90 — no more trips to Geneva for birth certificates.
New compensation philosophy and salary structure
The village hasn't had a formal pay structure for non-union staff since the recession stalled a 2007 study. A new 29-grade schedule aims to make pay competitive so the village stops losing trained employees; five staff below proposed minimums would be bumped up starting this year for about $16,000.
Bond refunding of 2014 general obligation bonds
The village wants to refinance its 2014 bond series, which has about eight years left. Savings were once projected at $200,000 but are now under $100,000 after interest rates rose, so the approved ordinance has no expiration date and lets staff act when the market improves.
Public works fleet replacement
Two big truck purchases totaling roughly $445,000 passed, but not without debate about replacing a 2014 truck with only 49,000 miles. Staff cited APWA scoring criteria and long delivery times.