Foxford Hills Lift Station No. 1 rehabilitation
The village awarded a $141,145 contract to replace worn-out pumps, rails, valves and controls at a sewer lift station, protecting against backups and service failures.
Water division truck replacement
A new 2027 Ford F-250 will replace the Water and Wastewater Division's 2016 truck that has reached the end of its useful life, purchased at cooperative bid pricing.
Wastewater digester improvements
The village hired IHC Construction to replace aging aeration equipment and slide gates at the wastewater plant for up to $1.4 million including contingency — essential infrastructure upkeep for sewer service.
2027 Water Main Replacement Program
The board hired Baxter & Woodman for construction engineering on the Bright Oaks water main project, budgeted at about $83,000 with contingency.
Street light electricity procurement through NIMEC
The village pools its buying power with 125 other northern Illinois municipalities to get cheaper electricity for street lights than ComEd's fixed rate. The administrator can now sign the lowest bid the same day it comes in.
Water and sewer rates and Well 14
Water/sanitation spending ($20M) outpaces revenue ($14M) this year by design, thanks to IEPA loan forgiveness for Well 14 and the five-year rate plan. A 5.9% rate hike keeps Cary competitive — actually low — compared to neighbors.
EV Charging at Metro Lot Rejected for Now
Staff proposed two EV chargers at the Metro commuter lot costing four parking spaces. The board pulled it from the plan, saying the Village can't afford to fund it, but left the door open for grants.
Well 3 Pump and Motor Replacement
Work found scale buildup in the well casing, requiring an extra $16,925 — but the project still comes in about $26,000 under budget.