South Slope WWTP improvements
The $114 million sewage treatment rebuild is 25% done, on schedule, with change orders at just 0.5% of the contract. The old activated sludge plant is offline and the RBC plant is carrying the load through a wet summer; completion is due November 2029.
PFAS Treatment at Water Treatment Plant
The city is applying for a $171,000 state grant to add variable frequency drives to two water plant pumps, cutting long-term energy costs with a $19,000 city match.