6 issues in water utilities
2026 Sanitary Sewer Rehabilitation and CDBG Funding
The consent package locked in engineering for the 2026 sanitary sewer rehabilitation (up to $141,500), Phase II street resurfacing design, and reimbursement financing for the Polaris Park flood control project.
Lead Service Line Replacement and Water Inventory
The village approved up to $554,525 for engineering services in 2026 to replace lead water service lines — the aging pipes that can leach lead into drinking water. Work will hit neighborhoods as lines get swapped out.
Polaris detention project completion
The stormwater detention project is moving along — excavation is 70% done, the field underdrain about half done, with grass planting expected in August-September. A main storm drain along 105th Street means torn-up streets, but officials say it'll benefit the whole district.
Regional Water System transmission main change orders
The board approved nearly $976,500 in additional change orders for the water transmission main project (Bid Package No. 5). This ongoing infrastructure work affects water service reliability for village residents.
Retention (stormwater) project near completion
The Polaris Field detention project is ahead of schedule, with field excavation 70% done and the storm drain reaching 105th Street. Residents face street closures for a couple more months.
Golf course restoration landscaping contract
Liebe Construction Services gets the landscaping contract for the golf course restoration piece of the Oak Lawn Regional Water System Improvements, with bidding waived.