2026 Sanitary Sewer Rehabilitation and CDBG Funding
The consent package locked in engineering for the 2026 sanitary sewer rehabilitation (up to $141,500), Phase II street resurfacing design, and reimbursement financing for the Polaris Park flood control project.
Special Homestead Exemption Home Building Program
The village plans to hire Leeside Builders to construct homes on roughly a dozen nuisance, tax-delinquent properties it has acquired, starting with two homes. New homes would come with 10 years of tax rebates to attract young families, and Desmond resigned to lead the effort.
2027 Street Resurfacing Program Engineering
The Traffic & Safety Commission wanted a two-way stop, but Trustee Mallo — a former driver's ed instructor who called the intersection one of the most dangerous on his routes — pushed it to a four-way. The Board agreed unanimously.
Police Union Collective Bargaining Agreement
A resolution was on the agenda to approve the village's contract with the Metropolitan Alliance of Police, Chapter #309 — the agreement that sets police pay and working conditions.
St. Linus Turkey Trot 5K Fee Waiver
The Lions Club's 16th annual 5K got approved, but Sunday overtime for Public Works pushes village costs to $7,268. The mayor asked the club to consider a Saturday date next year to cut costs.
Lead Service Line Replacement and Water Inventory
The village approved up to $554,525 for engineering services in 2026 to replace lead water service lines — the aging pipes that can leach lead into drinking water. Work will hit neighborhoods as lines get swapped out.
Proposed 2027 Budget
Trustee Mallo flagged that Illinois has cut the village's share of local government distributive fund money from 10% down to 6%, costing the village millions that could fund pensions and police. The Southwest Conference of Mayors is lobbying to restore it.
Home-based firearm dealer license ordinance
A proposed ordinance would amend Village business and zoning regulations to create license classes for gunsmithing, firearm transfers, and home-based firearm dealers — new rules affecting where and how these businesses may operate in the Village.
2027 Sidewalk and Concrete Repair Programs
Two proposed contracts with Dale, Inc. would fund removal and replacement of public sidewalks (up to $49,500) and curb, gutter and driveway concrete (up to $275,000) in 2027. The 50/50 sidewalk program typically shares costs with property owners.
McCormick lawsuit settlement
A second proposed settlement agreement in the Mary McCormick lawsuit against the Village was on the consent agenda.
Mabon lawsuit settlement
The Village was set to consider paying $125,000 to settle a lawsuit over an August 2025 accident in which a police officer made a U-turn on 95th Street and struck a driver's vehicle. The original demand was $500,000; negotiations brought it down to $125,000.
Third-party plan review cost reimbursement
A proposed building-code amendment would allow the Village to pass through or reimburse third-party plan review costs as part of building permits, potentially affecting permit fees for new construction and remodels.
March 17 election and early voting
The Clerk's report was scheduled to include election information, following early voting that began at the Oak Lawn Library on October 19 and ran through November 2.
2027 Tree Pruning and Removal Services Contract
The village awarded a $520,160 contract to Smitty's Tree Service for next year's tree trimming and removal work across the village.
Storm debris cleanup progress
Public Works removed roughly 875 tons of tree debris plus 400 tons of lighter debris after one of the worst storm seasons in memory. Residents with remaining debris should contact the village, but backyard branch pickup won't continue.
Polaris detention project completion
The stormwater detention project is moving along — excavation is 70% done, the field underdrain about half done, with grass planting expected in August-September. A main storm drain along 105th Street means torn-up streets, but officials say it'll benefit the whole district.
Regional Water System transmission main change orders
The board approved nearly $976,500 in additional change orders for the water transmission main project (Bid Package No. 5). This ongoing infrastructure work affects water service reliability for village residents.
Fire apparatus Unit E2 emergency repairs
The village's 2008 fire engine is out of service due to frame and pump problems. The board approved up to $93,056.11 in repairs to extend its life about two years while a replacement is procured; a reserve truck will cover responses in the meantime.
Underage e-scooter and mini-bike safety
Police wrote 18 citations last weekend as enforcement of the village's e-scooter ordinance ramps up, after two girls riding a scooter were struck by a car. Officials are circulating a one-page explainer to schools and social media explaining who can legally ride what.
Retention (stormwater) project near completion
The Polaris Field detention project is ahead of schedule, with field excavation 70% done and the storm drain reaching 105th Street. Residents face street closures for a couple more months.
Nycor infrastructure project update
The year-long water/infrastructure project from 87th to 93rd Street lagged until July; now under weekly oversight, the contractor says it will finish before the snow flies.
Police accountability and treatment of Arab community
Roughly 18 speakers, most from outside the village, demanded accountability for Oak Lawn police conduct, including the failure to test a driver who killed Murad Kurdi in 2023 and the forceful removal of a 14-year-old from an August 5 Fire and Police Commission meeting. Many demanded the board request an independent Attorney General investigation. The board took no action during the meeting.
O.A.K. Residential Construction and Sales Program
Through the consent agenda, the board created a new village housing program — O.A.K. (Opportunity, Affordability, Keystone) — authorizing construction and sale of homes, including waiving competitive bidding so the village can negotiate directly with general contractors.
Clean FY2025 audit
Independent auditors Baker Tilly gave the village the best opinion possible — clean, with no complaints and no internal-control findings. Pension funds grew by $28.4 million to about $219 million.
Security fogger ordinance targets gaming burglaries
Crews are smashing into video gaming businesses across the Southland in under two minutes, including one Oak Lawn hit the morning of the meeting. The mayor is pushing the stalled one-penny-per-push tax and blaming state sentencing rules for repeat offenders.
Polaris Stormwater Detention Project
Trustee Soch told District 6 residents the stormwater pipe retention project is actually a bit ahead of schedule, despite temporary water, cable, and internet disruptions during construction. He asked for patience and pointed residents to the project hotline on the village website.
Backyard chickens request
A young resident asked the board to allow a few backyard chickens for eggs. The mayor said it's been raised before and comes down to rodents and health concerns — no change coming.
Nicor Gas Restoration Failures
Residents on Austin Avenue got no notice of gas main work on their properties, and the 89th-to-93rd Street project has left torn-up sidewalks for nearly a year. Trustees unloaded on Nicor reps, who agreed to weekly check-ins and better notification — including possible door hangers via village staff.
Nycor construction project delays
The Nycor project in District 2, started back in 2015's funding cycle, still isn't done and now won't finish until October. Trustee Olejniczak wants a full timeline and accountability; Nycor will appear at the July 28 meeting.
District 1 Trustee vacancy filled
Tim Desmond's resignation leaves District 1 without a trustee until the 2027 election. The mayor wants resumes by May 20 and will interview candidates before appointing someone with board consent.
New Ambulance Cots for Fire Department
The village skipped competitive bidding to buy five powered ambulance cots and power-load systems for the fire department — equipment that protects paramedics' backs and speeds patient loading.
$15.5 Million General Obligation Bonds, Series 2026
The village is borrowing up to $15.5 million, with a direct annual tax levy pledged to pay back principal and interest.
2026 Street Program - Phase 2
Lindahl Brothers will resurface village streets this year under a contract up to $3,379,521.87.