  • ZBA-2026-0040 Louck Farms LLC Rezone

    Louck Farms LLC wants 4.75 acres rezoned from Rural Residential to Agriculture to expand a future building site.

    still pending

    Track this project →
  • Michael P Cochran Special Use

    Michael P Cochran seeks a special use to split 5 acres off a 40-acre agricultural tract, below the standard 25-acre minimum lot size.

    still pending

    Track this project →
  • Michael P Cochran Zoning Case

    A special use allowing a 5-acre split from a 40-acre farm so the owners can build a house; the test well produced 3.75 gallons per minute.

    approved (16-0) · still approved

    Track this project →
  • Louck Farms LLC Zoning Case

    A 4.75-acre rezone from rural residential to agriculture so the owners can realign boundaries with 150 adjacent acres before building a new house.

    approved (16-0) · still approved

    Track this project →

Also discussed

  • County Road Construction Engineering Contracts

    Stark Excavating holds low bids to repair the Airport Road bridge ($189,436) and rehabilitate the Willow Knolls Road bridge ($1.4 million).

    What it means: About $1.59 million combined for both bridge projects.

    Follow this issue →
  • Bridge Repairs on Airport and Willow Knolls Roads

    Stark Excavating holds low bids to repair the Airport Road bridge ($189,436) and rehabilitate the Willow Knolls Road bridge ($1.4 million).

    What it means: About $1.59 million combined for both bridge projects.

    Follow this issue →
  • Courtroom 321 Renovation Procurement Pivot

    Two courthouse remodels totaling nearly $2.9 million are on the consent agenda: Courtroom 321 and the Main Street lobby and south vestibule.

    What it means: About $2.9 million combined in county capital spending.

    Follow this issue →
  • Food Safety Ordinance Revisions

    The county health department's proposed updates to Chapter 10 Food Safety Ordinance would change the rules for food businesses in the county.

    What it means: Diners and food businesses that would get clearer, updated rules.

    Follow this issue →
  • Koerner Road Resurfacing Project

    Two contracts totaling about $1.06 million would resurface Koerner Road, with engineering by Millennia Professional Services and construction by R.A. Cullinan & Son.

    What it means: About $1.06 million combined between engineering and construction.

    Follow this issue →
  • Small-business microgrant program continuation

    The board added $75,000 to keep giving $5,000 microgrants to entrepreneurs, funded from the CDAP fund rather than property taxes. Members pressed for better data and quarterly reporting on outcomes.

    What it means: $75,000 from an $800,000 CDAP fund balance; no property tax dollars involved.

    Follow this issue →
  • FY27 Annual Budget and Tax Levy Adoption

    The county kept its tax rate flat at 82.41 cents, but a 6% jump in property values means most tax bills will still rise. Dissenting members want the county to cut its take instead, and the budget puts roughly $10 million toward jail improvements.

    What it means: Roughly $2.2 million more in county property tax revenue next year on a $183 million budget.

    Follow this issue →
  • CO2 storage project public meeting

    Three residents urged the board to impose a 12-month moratorium on carbon sequestration — including test wells and CO2 trucking — tied to a Lapis Carbon Solutions project near Texas and Cottonwood Roads, until the county writes zoning standards. Other Illinois counties have done the same; the board took no action, saying it is still learning its authority.

    What it means: Companies could earn roughly $36 million a year in federal tax credits while the county and township bear road wear and emergency-response risk with no guaranteed revenue.

    Follow this issue →
  • County Facilities Roadmap and Hannah City Work Camp Demolition

    Retiring member Phil Salzer used his farewell to urge the public and the board to get behind building a new jail, warning the chief judge could close the current one. The budget includes $3.5 million for jail master plan design.

    What it means: Jail needs are estimated around $30 million; FY27 budgets $3.5 million for design and engineering.

    Follow this issue →
  • Infrastructure and Roadway Projects

    The board approved the Koerner Road resurfacing bid ($979,848.73), Airport Road bridge repair ($189,436.29), and Willow Knolls bridge rehab ($1.4 million) on the consent agenda.

    What it means: About $2.6 million combined across the three projects.