Peoria County · week of November 1, 2026

Council approves Four Creeks Wind Project Special Use Permit (ZBA-2026-0037), 4–2

Summarized from the official meeting transcript — every claim links to the moment it was said. How we make this

What changed in Peoria County

  • Four Creeks Wind Project Special Use Permit (ZBA-2026-0037)

    4 yes, 2 no

    Betty Duncan (yes), James C. Dillon (no), Steven B. Rieker (yes), Terry Ruhland (no), Matt Windish (yes), Paul Rosenbohm (yes)

    Watch this moment →

Development activity

  • Zoning Case ZBA-2026-0037

    Four Creeks, LLC has filed a zoning case (ZBA-2026-0037) that the Land Use Committee is scheduled to consider on November 5.

    Discussed — no decision yet

    Track this project →
  • Four Creeks Wind

    Brimfield, Millbrook, Princeville, and Jubilee Townships, Peoria County, IL

    A special use permit for up to 113 wind turbines (max 657 feet tall) and 663 MW of capacity, approved with 36 county conditions including 100% decommissioning funding, five-year sound studies, and shadow flicker curtailment.

    approved (12-5) · still approved

    Track this project →

Also discussed

  • Four Creeks, LLC zoning petition (ZBA-2026-0037)

    A 113-turbine, 663-megawatt wind facility across ~27,000 acres of western Peoria County was approved with 36 restrictions after the ZBA recommended denial. The decision will shape the rural landscape, tax base, and development potential of the area for roughly 40 years.

    What it means: Over $300 million in property taxes over the project's life, with schools expected to receive more than $7 million in year one, plus lease income to participating farmers.

    Raised 2 times this week

    Follow this issue →
  • Zoning Petitions Review

    Four Creeks, LLC has a zoning case before the county, and the Land Use Committee is set to consider it Thursday. What the committee recommends could shape how the affected property can be used.

    What it means: The petitioner and any residents interested in the property's future use.

    Follow this issue →
  • Four Creeks Wind Energy Road Use Agreement

    A developer wants to build up to 113 wind turbines — some 657 feet tall — across about 27,000 acres of farmland in four northern Peoria County townships. Supporters typically point to lease payments and tax revenue; opponents raise concerns about noise, views, and property values.

    What it means: Participating landowners receiving lease payments, the county through potential tax revenue, and renewable energy buyers.

    Follow this issue →

Published by Illinois Record. 2 meetings covered.