Burlington Avenue realignment and downtown parking
crews hit far more contaminated soil than the design anticipated, adding $177,869 and pushing the project to about $1.8 million.
4 mentions (1 this month)Last discussed Nov 12, 2026
HighRoads
Metra station renovation advances via BNSF lease termination
Metra is spending $22 million to renovate the Westmont depot — heated platforms, full building remodel, accessibility upgrades. The village waived permit fees (roughly $10,000–$30,000 in real cost) to make it happen, calling it a long-overdue win.