Foxford Hills Lift Station No. 1 rehabilitation
The village awarded a $141,145 contract to replace worn-out pumps, rails, valves and controls at a sewer lift station, protecting against backups and service failures.
Water division truck replacement
A new 2027 Ford F-250 will replace the Water and Wastewater Division's 2016 truck that has reached the end of its useful life, purchased at cooperative bid pricing.
Wastewater digester improvements
The village hired IHC Construction to replace aging aeration equipment and slide gates at the wastewater plant for up to $1.4 million including contingency — essential infrastructure upkeep for sewer service.
2027 Water Main Replacement Program
The board hired Baxter & Woodman for construction engineering on the Bright Oaks water main project, budgeted at about $83,000 with contingency.