Wastewater Treatment Plant UV Disinfection Conversion
The 45-year-old sludge building has only about five years of life left, so the village is accelerating $1.6 million in engineering now. A $1.87 million UV disinfection project was also moved up to save mobilization costs and reduce chlorine storage.
Jacobson Avenue retention pond problems
Residents in Trustee Siddiqi's district have complained about retention ponds; he's arranging a meeting between them and public works to find a fix.
New water billing portal
The finance department announced a new online portal for paying water bills, viewing usage and payment history, coming soon.
CDBG Jill Court and Maryland Avenue Water Main Replacement
The village is replacing aging water mains at $1.3 million a year but the master plan says $1.74 million is needed. The fee on your water bill funds this — and increases planned through 2028 may need to continue beyond that.
Wastewater Treatment Plant Investment
State EPA nutrient-removal mandates will require major plant expansion, with some buildings dating to 1959, funded through low-interest loans, rates and grants.
Residential service line warranties
Aging water and sewer lines in Glendale Heights neighborhoods — some 25 to 60 years old — fail frequently, with replacements costing $10,000-$12,000 or more. The proposed HomeServe program gives residents a voluntary, village-endorsed way to insure against those costs, though the village only markets it rather than running it.