Airport fuel tank construction completion
New fuel tanks should be running by May or early June, but construction will close part of the ramp and Taxiway Alpha-3 starting mid-March. Pilots will still have fuel and west tie-downs, with only brief fuel outages.
Solid Waste Truck Financing
The council expanded a lease of side-load garbage trucks from two to three, betting that buying before 2027 federal emissions rules take effect saves money and avoids proprietary-parts headaches with the current drop-frame chassis.
Fiber Data Service for City Facilities
A service agreement with Bluebird Fiber would supply data connections to the wastewater treatment plant and pocket parks. Reliable connectivity supports plant operations and park services.
Willow Street sewer main repair
Council approved a $32,300 emergency repair of the Willow Street sewer main; digging starts the next morning.
Williamsburg Court Drainage Dispute
Rex Pogioli says city and apartment runoff has eroded his property for decades. The city manager and city engineer explained the erosion stems mostly from the apartment complex's private storm sewer, and repairs on private property are the owners' responsibility before city work can proceed.
Court Street Stormwater Relocation Project
The city is funding engineering to relocate the stormwater pond on Court Street as part of the public infrastructure for the one-acre land sale in front of Menards; the buyer, JPG, will perform the physical work at its own expense.
East Court Village Drainage Project and Budget Amendment
A proposed $2 million fix for the eroding creek behind East Court Village was tabled because the creek falls under Army Corps jurisdiction, adding a 12-18 month permitting process. A resident argued TIF money for the creek should entitle lakefront owners to use residential TIF funds for dredging.
Sewer Lining Project Expansion
The terminal building keeps having sewer backups from a corroded cast-iron pipe. The fix: dig up a couple parking spots to install a permanent cleanout so the line can be mechanically cleaned. Estimates are being gathered.
Storm water emergency near Ashwood Lane
Creek bed erosion near Ashwood Lane has exposed a natural gas main that appears to be collapsing. The council pre-authorized emergency spending so the city can act immediately if a dangerous leak develops, while the gas company and city sort out responsibility.
FCI Pekin Wastewater Contract
The federal prison needed a formal contract before remitting wastewater payments delayed by a government shutdown. Nutter questioned whether the provision covered only the last shutdown; the city attorney confirmed it is limited to a discrete period.