Top issues during term (13)(Roads)
Seil Road bridge replacement and reconstruction
$8.9 million construction bid administered through IDOT.
New traffic signal at Wynstone and Route 52
Part of the $1.008 million signalization project, currently 43% complete.
Route 52 signal and YMCA opening
Projected economic impact of more than $8 million next year.
D Construction lease on Frontage Road
Lease revenue continues through May 2027; no figures were given.
Winter road salt supply shortage
Up to $250,000, already budgeted, for 2,000 tons of road salt.
Vertin Boulevard Traffic Calming
Speed humps cost up to $50,000, purchased from Traffic Logix.
Rock salt purchasing agreement for 2026-27 winter
About $250,000 budgeted for roughly 2,500 tons of salt.
Mound Road Bridge maintenance
About $600,000 planned for construction, with $58,960 approved now for design.
2027 street resurfacing program
Engineering capped at $119,475 within an estimated $1.5 million program budget.
Route 52 and County Line safety concerns
Traffic congestion on Black Road and Route 59 corridor
All Black Road traffic improvements, including the signal upgrade, are at the developer's expense.
Pavement condition survey of Village roadways
Up to $60,000, helping target future resurfacing dollars efficiently.
Route 52/59 street lighting replacement costs
A full decorative replacement would create a $3–5 million deficit in the five-year capital plan.
Decisions during term (0)
Recorded while DeBold was in office — not necessarily decisions they moved, spoke to, or voted on.
No decisions found matching Roads.
Voting record (0)(Roads)
No votes found matching Roads.