10 issues in roads with medium priority
Downtown Cass Avenue Streetscape Improvements
Ancient controllers at four intersections get replaced, which should stop the Richmond signal from fighting the others and backing up traffic.
Railroad Underpass Project Dropped
The finance committee concluded the village can't afford the railroad underpass — costs have ballooned far beyond the original estimate — and recommended not moving forward for now.
Grade-separated pedestrian crossing grant pursuit
The village will chase up to $2 million in state ITEP funding for a pedestrian crossing at the Westbound train station, adding to $5 million already secured. Some trustees balked at a potential $500,000 local match, but the village can still walk away before signing agreements.
2026 Sidewalk Improvements
Susie Wayt objected to sidewalk work near her elderly parents' home on 65th Street that would remove trees and shrubs providing natural privacy — important because they care for a handicapped adult son. The mayor directed her to Public Works Director Ries.
Des Moines Street reconstruction
The board awarded the street rebuild to Schroeder Asphalt at a low bid about 15% under the engineer's estimate, hired the construction engineer, and appropriated $1.5 million in motor fuel tax funds.
S Curve Realignment Delayed
Construction on the S Curve realignment on Burlington stopped after crews hit an underground storage tank; work can resume once the fire marshal issues a permit.
Downtown Parking & Valet During Construction
Businesses got spooked by a construction notice that seemed to close the Cass/Burlington parking lot. Staff clarified the lot stays open most of the time, the newer Lincoln/Irving lot has more spaces, and a meeting with the Chamber is planned.
Residential Alley 7S Reconstruction
The next alley rebuild — between 55th and West Quincy, Washington to Hudson — goes to Schroeder Asphalt at a bid roughly 23% under estimate. Part of a worst-first alley program now in its fifth year.
KMED Relocation and S-Curve Project
KMED says it will clear the right-of-way by May 2026, letting the village tackle the S-curve road fix at the same time. A bid opening is set for February 24 with a contract award in March — delays could push the project back five years.
Road Construction Methods
Public Works followed up on road construction with a design engineer review: existing storm sewer can be reused, but the existing ditches are substandard and expensive to fix. Curb-and-gutter is the recommended drainage approach, with value engineering to keep the project in budget.