7 issues in water utilities

HighWater Utilities

North Elevated Water Storage Tank Completion

ComEd changed the electric hookup plan mid-construction, adding $143,275 and pushing the tower's electric run about 500 feet instead of the planned ~200. The tower should be online by end of 2026, and it's up for a national 'Tank of the Year' contest — residents can vote through October 16.

1 mentionLast discussed Oct 15, 2026
HighWater Utilities

1 N. Cass ComEd relocation

After nearly ten years, the village is paying ComEd's $1.6 million construction deposit to relocate utilities at 1 N. Cass. Construction, estimated at $2 million total, could start by September once the BNSF railroad permit arrives.

1 mentionLast discussed Jul 23, 2026
MediumWater Utilities

Community well conditions for annexed properties

Four properties annexed in 2025 share a community well. The amendment keeps them on the well unless it fails, so one owner can't cut off water for the other three.

2 mentionsLast discussed Jul 23, 2026
LowWater Utilities

Fairfield recapture agreements retired

Old water-connection fee agreements from 2011 are being wiped off the books for 11 properties because the developer no longer exists — removing a title cloud that discouraged connections.

1 mentionLast discussed Jul 23, 2026
LowWater Utilities

Water safety — PFAS testing results

Good news: testing for 29 PFAS chemicals and lithium in Westmont's water found nothing detectable. Postcards went to all water customers.

1 mentionLast discussed Mar 5, 2026
LowWater Utilities

Fiber Internet and Cybersecurity Agreements

Ripple Fiber became the third fiber provider licensed in town, with service expected later in 2026, and the village locked in a 3-year UncommonX security operations contract.

1 mentionLast discussed Jan 8, 2026
HighWater Utilities

Stormwater Code Revisions

Current rules are so strict that adding even one square foot of new pavement triggers detention for the whole property — one business owner's retention requirement cost over $250,000. Adopting the county's 25,000-square-foot threshold would make redevelopment much easier, with three local amendments layered on for flood-prone areas.

1 mentionLast discussed Jan 8, 2026