2 issues in water utilities with high priority
North Elevated Water Storage Tank Completion
ComEd changed the electric hookup plan mid-construction, adding $143,275 and pushing the tower's electric run about 500 feet instead of the planned ~200. The tower should be online by end of 2026, and it's up for a national 'Tank of the Year' contest — residents can vote through October 16.
1 N. Cass ComEd relocation
After nearly ten years, the village is paying ComEd's $1.6 million construction deposit to relocate utilities at 1 N. Cass. Construction, estimated at $2 million total, could start by September once the BNSF railroad permit arrives.