5 issues in water utilities

HighWater Utilities

2026 Sanitary Sewer Rehabilitation and CDBG Funding

The consent package locked in engineering for the 2026 sanitary sewer rehabilitation (up to $141,500), Phase II street resurfacing design, and reimbursement financing for the Polaris Park flood control project.

5 mentions (1 this month)Last discussed Nov 10, 2026
HighWater Utilities

Lead Service Line Replacement and Water Inventory

The village approved up to $554,525 for engineering services in 2026 to replace lead water service lines — the aging pipes that can leach lead into drinking water. Work will hit neighborhoods as lines get swapped out.

4 mentions (1 this month)Last discussed Nov 10, 2026
HighWater Utilities

Polaris detention project completion

The stormwater detention project is moving along — excavation is 70% done, the field underdrain about half done, with grass planting expected in August-September. A main storm drain along 105th Street means torn-up streets, but officials say it'll benefit the whole district.

3 mentionsLast discussed Oct 13, 2026
HighWater Utilities

Regional Water System transmission main change orders

The board approved nearly $976,500 in additional change orders for the water transmission main project (Bid Package No. 5). This ongoing infrastructure work affects water service reliability for village residents.

1 mentionLast discussed Oct 13, 2026
HighWater Utilities

Retention (stormwater) project near completion

The Polaris Field detention project is ahead of schedule, with field excavation 70% done and the storm drain reaching 105th Street. Residents face street closures for a couple more months.

2 mentionsLast discussed Sep 8, 2026